Skip to main content
In order to ensure that Charlton Town officials and members of the community remain engaged and informed of the Project’s development and construction plans, the Northeast Energy Center (NEC) has been working to establish and maintain regular and open lines of communication. The Project team has been in regular contact with the Charlton Town Administrator; who in return has been providing regular briefs to the Board of Selectmen and other Charlton officials on project activities. Additionally, NEC has held multiple meetings with the Board of Selectmen, the Charlton Economic Development Council, the Charlton Fire Department, the Town Planner, the Building Commissioner, and the Tax Assessor. The NEC Project construction is now complete and is in the commissioning and startup phase. The Facility will be ready for commercial operations April 2024.

Project Timeline

Date
Activity
October 2021 MA Energy Facility Siting Board (EFSB) Approval Received
November 2021 MassDEP (Air & Noise) Approval Received
February 2022 Prime Contractor Mobilization to Site
February – March 2022 LNG Site Clearing & Grubbing
March – May 2022 LNG Site Rough Grading
August – December 2022 Meter Station Installation
May 2022 – February 2023 LNG Storage Tank Erection
September – December 2022 Interconnection Pipeline Installation
October 2022 Complete Major Foundations 
March 2023 Set Major Equipment 
December 2023 LNG Facility Mechanical Completion 
April 2024 Facility Ready For Commercial Operations 

Have a question? Contact us today!